10th Street NW Storm Sewer Improvement Project

Project Description

This project required the installation of 3,200 linear feet of concrete pipe storm sewer with pipe sizes reaching 54” in diameter. The project also was designed with 37 storm sewer structures the largest being a 96” diameter manhole. Over 235 cubic yards of solid rock was encountered on this project which required systematic jackhammering and removal. To repair the street and driveways in the excavation area, over 4,800 square yards of 7” pavement was placed.